Employer: ENEL S.p.A. on behalf of ENEL PRODUZIONE S.p.A, Italy
Contractor: Geotechmin OOD
Project implementation period: 2007 – 2008
Description of the project:
The project is executed on the territory of Maritza East III thermoelectric power plant in the conditions of uninterrupted plant operation. It includes the following subprojects:
- Two Oily Water Treatment Basins
- First-Flush Rainfall Water Basin (35 m x 20 m, depth 4 m)
- Lagoon Water Collecting Pit
- Buffer Pond (storage capacity 30 000 cub.m.) – a basin with soil bottom and embankments and waterproofing of HDPE flexible geo-membrane
- Foundations for a Dosing Device for Cooling Water Chemicals
- Repair of the Foundations of the Pump Stations for Purified and Sluice Water
- Buried yard piping connecting new utilities to existing ones
Conducted works:
- excavation works – 24,000 cub.m.
- filling and backfilling works – 71,000 cub.m.
- concrete works – 1,700 cub.m.
- formwork – 2,700 cub.m.
- reinforcement works – 134 tons
- reinforced concrete pipes – 690 m
- PVC pipelines – 400 m
- GRP pipelines – 1,100 m
- metal structures – 15 tons