Employer: ENEL S.p.A. on behalf of ENEL PRODUZIONE S.p.A, Italy
Contractor: Geotechmin OOD
Project implementation period: 2007 – 2008

Description of the project:
The project is executed on the territory of Maritza East III thermoelectric power plant in the conditions of uninterrupted plant operation. It includes the following subprojects:

  • Two Oily Water Treatment Basins
  • First-Flush Rainfall Water Basin (35 m x 20 m, depth 4 m)
  • Lagoon Water Collecting Pit
  • Buffer Pond (storage capacity 30 000 cub.m.) – a basin with soil bottom and embankments and waterproofing of HDPE flexible geo-membrane
  • Foundations for a Dosing Device for Cooling Water Chemicals
  • Repair of the Foundations of the Pump Stations for Purified and Sluice Water
  • Buried yard piping connecting new utilities to existing ones

Conducted works:

  • excavation works – 24,000 cub.m.
  • filling and backfilling works – 71,000 cub.m.
  • concrete works – 1,700 cub.m.
  • formwork – 2,700 cub.m.
  • reinforcement works – 134 tons
  • reinforced concrete pipes – 690 m
  • PVC pipelines – 400 m
  • GRP pipelines – 1,100 m
  • metal structures – 15 tons

History

Truck

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet.

Storage

Vero eros et accumsan et iusto odio dignissim qui blandit praesent luptatum zzril delenit augue duis dolore te feugait.

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat volutpat. Ut wisi enim ad minim veniam, quis nostrud exerci tation ullamcorper.

This website uses cookies, if you continue to use our website you confirm that you consent with our cookies policy.