Employer: Umicore Med AD
Designer and contractor: Geotechmin OOD
Project implementation period: 2001 – 2002

Description of the project:
The project includes design and construction of a covered storage facility for metallurgical waste generated by the activities of Umicore Med. The total area of the storage is 3 200 sq.m. Its walls are 4 meters high with built-in steel plates for protection against demolition by loading machines. The steel roof structure and the walls are coated in LT-sheet steel and PVD-screen for protection from the aggressive environment.

Conducted works:

  • concrete works – 2,354 cub.m.
  • formwork – 3,700 sq.m.
  • reinforcement – 190 tons
  • HDPE smooth liner, 2 mm thick – 14,050 sq.m.
  • steel structure – 205 tons
  • steel plates, 20 mm thick – 27 tons
  • demolition of reinforced structures and elements – 14,050 cub.m.
  • crushing of reinforced concrete pieces and separation of construction steel – 14,050 cub.m.
  • demolition of concrete structures and elements – 21,630 cub.m.
  • landfilling of contaminated concrete – 21,630 cub.m.
  • construction of an asphalt road – 1.3 km
  • construction of an asphalt platform – 2,100 sq.m.
  • loading and transportation to a landfill of contaminated soil – 4,100 sq.m.

History

Truck

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet.

Storage

Vero eros et accumsan et iusto odio dignissim qui blandit praesent luptatum zzril delenit augue duis dolore te feugait.

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat volutpat. Ut wisi enim ad minim veniam, quis nostrud exerci tation ullamcorper.

This website uses cookies, if you continue to use our website you confirm that you consent with our cookies policy.