History

Employer: Helix EOOD
Designer: Geoproject EOOD
Contractor: Geostroy AD
Project implementation period: 2012 – 2014

Description of the project:
The installation produces vermiculite concentrate and exfoliated vermiculite by processing and enrichment of raw vermiculite, which is extracted from Livade quarry near the village of Belitsa, Ihtiman Municipality.

The general contractor of the project Geostroy AD has built the following subprojects: indoor premises of the vermiculite separating installation with three main sections: raw vermiculite storage, separating facility and finished product storage; silos for waste materials; ancillary structures – service building, weighbridge and transformer substation. The work scope also includes landscaping, external water sewerage and electricity connections, site fencing.

History

Truck

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet.

Storage

Vero eros et accumsan et iusto odio dignissim qui blandit praesent luptatum zzril delenit augue duis dolore te feugait.

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat volutpat. Ut wisi enim ad minim veniam, quis nostrud exerci tation ullamcorper.

This website uses cookies, if you continue to use our website you confirm that you consent with our cookies policy.