Technical and biological reclamation of disturbed terrains in Ellatzite-Med
A number of projects and initiatives have been undertaken to implement the Environment Protection and Recovery Programme for the Region of Ellatzite Deposit. One of them is the technical and biological reclamation of disturbed terrains. To date, approximately 30.5 hectares have been technically and biologically reclaimed at the East Waste Dumps, as well as more than 29 hectares at Benkovski-2 Tailings Pond.
The technical and biological reclamation of the downstream face areas of Benkovski-2 Tailings Pond will be completed in 2026.
Employer and Contractor:
Ellatzite-Med ADDesigner:
Geoproject EOODProject implementation period:
2010-2026Date:
June 2023