History

Employer: Umicore Med AD
Designer and contractor: Geotechmin OOD
Project implementation period: 2002 – 2003

Description of the project:
After closing of Small Lagoons landfill for waste slurries due to exhaustion of its capacity, Umicore Med entrusted Geotechmin with the construction of a new landfill for calcium-arsenate cakes. This was the second stage of the project for extension of the capacity of the Small Lagoons.

The landfill design is fully compliant with Ordinance No.13/1998 which transposes the EU Landfill Directive and Ordinance No.26/1996 on Rehabilitation of Contaminated Sites.

The total area of the landfill for calcium-arsenate cakes is 14 decares and its volume is 68,000 cub.m.

Conducted works:

  • HDPE waterproof liner (2 mm thick with UV protection) – 12,700 sq.m.
  • drainage system on top of the waterproof liner – 380 m
  • system for leading of waters under the liner – 520 m
  • geotextile (500 gr per sq.m.) – 3,800 sq.m.
  • geosynthetic bentonite membrane – 10,130 sq.m.
  • clay fill – 2,670 m

History

Truck

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet.

Storage

Vero eros et accumsan et iusto odio dignissim qui blandit praesent luptatum zzril delenit augue duis dolore te feugait.

Lorem ipsum dolor sit amet, consectetuer adipiscing elit, sed diam nonummy nibh euismod tincidunt ut laoreet dolore magna aliquam erat volutpat. Ut wisi enim ad minim veniam, quis nostrud exerci tation ullamcorper.

Този сайт използва бисквитки, ако продължите да използвате сайта ни вие се съгласявате с нашата политика за бисквитките.